Line 29: Line 29:
 |**Runoff control** - Diversions, dikes, and outlet protection|Install key practices after principal sediment traps and before land grading.  Install additional practices during grading.| |**Runoff control** - Diversions, dikes, and outlet protection|Install key practices after principal sediment traps and before land grading.  Install additional practices during grading.|
 |**Runoff conveyance system** - Stabilize stream banks, storm drains, channels, inlet and outlet protection, channels, and slope drains|Where necessary, stabilize stream banks as early as possible.  Install principal runoff conveyance system with runoff control measures.  Install remainder of system after grading.| |**Runoff conveyance system** - Stabilize stream banks, storm drains, channels, inlet and outlet protection, channels, and slope drains|Where necessary, stabilize stream banks as early as possible.  Install principal runoff conveyance system with runoff control measures.  Install remainder of system after grading.|
-|**Land clearing and grading** - Site preparation, cutting, filling and grading, [[sediment trap|sediment traps]], barriers, drains, diversions, surface roughening|Begin major clearing and grading after principal erosion control practices have been installed.  Clear and grade only as needed.  Install additional measures as necessary.  Mark trees and buffer areas for preservation.| +|**Land clearing and grading** - Site preparation, cutting, filling and grading, [[sediment trap]], barriers, drains, diversions, surface roughening|Begin major clearing and grading after principal erosion control practices have been installed.  Clear and grade only as needed.  Install additional measures as necessary.  Mark trees and buffer areas for preservation.| 
-|**Surface stabilization** - [[Seeding]], [[native plants|native grasses]], [[mulching]], [[sod|sodding]], and riprap|Apply temporary or permanent stabilization measures immediately on all disturbed areas where work is delayed or complete.|+|**Surface stabilization** - [[Seeding]], [[native plants]], [[mulching]], [[sod|sodding]], and riprap|Apply temporary or permanent stabilization measures immediately on all disturbed areas where work is delayed or complete.|
 |**Building construction** - Buildings, utilities, and paving|Install necessary practices before work takes place.| |**Building construction** - Buildings, utilities, and paving|Install necessary practices before work takes place.|
-|**Infiltration Practices** - [[bioretention basin|bioretention basins]], [[infiltration basin|infiltration basins]], [[rain garden|rain gardens]], [[infiltration trench|infiltration trenches/beds]]|Must be installed during final stabilization or when runoff can be diverted and prevented from disturbing the site to avoid being filled with sediment during construction.|+|**Infiltration Practices** - [[bioretention device]], [[infiltration basin]], [[rain garden]], [[infiltration trench]]|Must be installed during final stabilization or when runoff can be diverted and prevented from disturbing the site to avoid being filled with sediment during construction.|
 |**Landscaping and final stabilization** - Topsoiling, trees and shrubs, [[seeding]], [[mulching]], [[sod|sodding]], riprap|Last construction phase - Stabilize all open areas, including borrow and spoil areas.  Remove and stabilize all temporary practices.| |**Landscaping and final stabilization** - Topsoiling, trees and shrubs, [[seeding]], [[mulching]], [[sod|sodding]], riprap|Last construction phase - Stabilize all open areas, including borrow and spoil areas.  Remove and stabilize all temporary practices.|
  
-:!:**Maintenance activities are required throughout the construction process. Inspections shall be performed at least weekly and after all storm events.  All necessary repairs shall be made immediately.**+:!: Maintenance activities are required throughout the construction process. Inspections shall be performed at least weekly and after all storm events.  All necessary repairs shall be made immediately.
  
 =====Construction and Maintenance===== =====Construction and Maintenance=====