A wet pond retains a permanent supply of water while also temporarily accumulating stormwater runoff. Its purpose is to reduce stormwater flow velocity and trap sediment and other associated pollutants. Stormwater enters the pond and is temporarily retained, allowing pollutants to settle out. Pollutants, such as metals, nutrients, sediment, and organic substances, are removed by the settling of particulates, biological uptake, consumption, and decomposition.

This practice can be used in residential, commercial, and industrial areas if the contributing watershed is large enough. Generally, the watershed should be at least 10 acres to ensure a constant supply of water to maintain water depth. Due to the permanent ponding of water, wet ponds can remove large amounts of pollutants and are more effective in removing plant nutrients than most other management practices. The large volume of storage helps to reduce peak discharges from storm events, which, in turn, reduces down-stream flooding while limiting streambank erosion.

Advantages

Disadvantages

Design

Forebay/Inlet

Forebays, which are separated from the rest of the pond by a wall or berm, receive runoff and prevent concentrated flow from entering, while allowing sediment to settle out. They simplifies maintenance by concentrating sediments and extending the holding capacity and life of the pond. Forebays should have an area equal to 10-25% of the pond’s surface area, with a length to width ratio of at least 2:1 to provide proper flow. Forebays should be located opposite of the pond’s outlet to increase detention time.

Volume and Surface Area

Each pond should be modeled and built according to the individual characteristics of the watershed in which it is being placed, as each watershed will have a different hydrologic makeup. There is a direct correlation between the size of the pond and the pollution removal rate. The larger the basin, the greater the removal rate of sediment and pollutants from the runoff. Each pond must be designed to handle the runoff produced from the 2 and 10 year, 24-hour storm event for its watershed, and also be able to safely pass the 100-year storm event. The volume should also be sufficient to provide for the storage of accumulated sediment as well as the runoff from these storm events.

The surface area of the pond will vary as well based on location; however, a minimum area of 0.25 acres is recommended to sustain the permanent ponding of water.

Shape

Wet ponds should be designed so that the previously held stormwater is replaced by the newer stormwater, a process referred to as plug flow. Plug flow allows the water to remain in the pond long enough to facilitate the settling of sediment and the adsorption of pollutants and sediment. Failure to achieve this results in “short-circuiting”. To avoid short-circuiting, the pond should be designed with a length to width ratio of 3:1 in either a long, narrow shape or a teardrop shape. These shapes encourage proper mixing of the water column and increase the amount of time the stormwater remains in the pond. In addition, these shapes lessen the amount of sediment stirring caused by wind, allowing pollutants to remain settled in the sediment. If these shapes are not feasible, structures that lengthen the flow path, such as gabions and baffles, should be installed.

Pond Slopes

The side slopes should not exceed a 4:1 ratio and should not be less than 10:1. Slopes in this range prevent excessive erosion and makes maintenance tasks both easier and safer, while providing enough slope to provide adequate drainage. Submerged slopes should consist of two types: an aquatic bench and the pool slopes. Aquatic benches should extend at least ten feet from the water’s edge and have a slope with a 10:1 ratio. This shallow area promotes the growth of aquatic vegetation and also improves safety, allowing someone who has fallen in to quickly regain his or her footing. Pool slopes are located toward the center of the pond beyond the aquatic shelf. These slopes will depend on the soil stability of the site, but in general should not exceed a 2:1 ratio, as banks are likely to become unstable at higher ratios.

Depth

Ponds should be constructed with an average depth of 3-6 feet, with depths varying throughout. Depths greater than 10 feet may encounter low oxygen levels and thermal stratification, and are generally not recommended unless measures are taken to ensure proper oxygen content. The aquatic shelf should include shallow areas with depths ranging from 6-18 inches to promote the growth of aquatic vegetation and to improve safety.

Sediment Control

Wet ponds should remove, at a minimum, 80% of the total suspended solids from the runoff generated from the site. To increase the effectiveness and the life of the pond, sediment forebays or other pretreatment devices may be used and are recommended. The design should incorporate sediment accumulation over a period of at least 25 years to ensure the proper holding capacity over the life of the pond.

Outlet

Each pond should have 2 outlet structures, a principle outlet and a de-watering outlet. The principle outlet slowly releases the water to the receiving waters, while the dewatering outlet, which is used on a limited basis, allows the pond to be drained quickly for maintenance purposes. Both types of outlets should allow access to maintenance personnel while restricting access to the general public.

Outlets should be designed with stability in mind and should be able to endure frost heave and settling. In addition, all outlets should be designed to resist obstruction, which may be accomplished in several ways, including the use of skimmers and trash racks.

Construction

Maintenance

:!: Maintenance costs are estimated at 3-5% of construction cost per year

Method to Determine Practice Efficiency

Wet ponds reduce the flow velocity of runoff, allowing suspended particles to settle out. In addition, these devices remove nutrients, heavy metals, and other pollutants from stormwater by utilizing several biological processes. The efficiency for this practice is dependent upon the size of the pond, the size of the drainage area, and other site characteristics. As a result, the efficiency for this practice must be calculated using factors unique to each site. For more information, refer to the Basin Efficiency page.

References