redevelopment

Redevelopment

Based on existing and proposed land cover, sites may need to meet redevelopment standards, new development standards, or a mixture of the two.

A stormwater permit is required for the following activities:

  • The cumulative addition of 20,000 square feet of impervious surface.
  • Development that requires a subdivision plat or a certified survey map.
  • Land disturbance exceeding four thousand square feet on a commercial, industrial, institutional or multifamily site.
  • Development deemed an environmental risk by the department.

New development performance standards apply to the following:

  • Sites that have added 20,000 square feet, or more, of impervious surface since August 21, 2001.

Redevelopment performance standards apply to the following:

  • Sites that have added less than 20,000 square feet of impervious surface since August 21, 2001.
  • Redeveloping of existing impervious surface.

If the site is a mixture of new development and redevelopment, the redevelopment performance standards apply only to “redeveloped impervious” surfaces. New development performance standards apply to all other pervious and impervious surfaces. Removing existing impervious to maximize “redeveloped impervious” surfaces is acceptable when the surfaces generate similar pollutant loads.

Example Scenarios

Existing conditions as of August 21, 2001.


Surface Type Legend


Scenario 1: Cumulative impervious less than 20,000 ft2


Scenario 2: Cumulative impervious greater than or equal to 20,000 ft2


Scenario 3: Cumulative impervious greater than 20,000 ft2 and replacement of existing impervious


Scenario 4: Cumulative impervious less than 20,000 ft2 through removal of existing impervious


Scenario 5: Cumulative impervious greater than 20,000 ft2 and replacement of existing impervious
redevelopment.txt · Last modified: 2022/05/19 16:33 by admin

Donate Powered by PHP Valid HTML5 Valid CSS Driven by DokuWiki