Line 15: Line 15:
   - Temporarily stabilize disturbed areas that will remain inactive for 14 days.   - Temporarily stabilize disturbed areas that will remain inactive for 14 days.
   - Permanently stabilize any portion of the site within 7 days of reaching final grade.   - Permanently stabilize any portion of the site within 7 days of reaching final grade.
 +  - Install and maintain a concrete washout. Chute washwater may not be dumped on the ground.
   - De-watering shall conform to DNR Technical Standard 1061 and may not increase erosion.   - De-watering shall conform to DNR Technical Standard 1061 and may not increase erosion.
   - Remove accumulated sediment from ditch checks and stone weepers when it reaches 1/2 of the device height.   - Remove accumulated sediment from ditch checks and stone weepers when it reaches 1/2 of the device height.
Line 22: Line 23:
 **Temporary Stabilization** **Temporary Stabilization**
 ^ ^Lbs per acre^  Lbs per 1,000 ft<sup>2</sup>  ^Season^ ^ ^Lbs per acre^  Lbs per 1,000 ft<sup>2</sup>  ^Season^
-|Summer Oats|130|3|Spring-Summer| +|[[seeding|Summer Oats]]|130|3|Spring-Summer| 
-|Cereal Rye|130|3|Fall| +|[[seeding|Cereal Rye]]|130|3|Fall| 
-|Winter Wheat|130|3|Fall| +|[[seeding|Winter Wheat]]|130|3|Fall| 
-|Annual Ryegrass|80|2|Spring-Fall| +|[[seeding|Annual Ryegrass]]|80|2|Spring-Fall| 
-|Straw Mulch|4,000|90|Year-round|+|[[mulching|Straw Mulch]]|4,000|90|Year-round| 
 +|[[mulching|Wood Chip Mulch]]|12,000|270|Year-round|
  
 **Permanent Stabilization** **Permanent Stabilization**
Line 35: Line 37:
 |Phosphorus-Free Fertilizer|150|3.4| |Phosphorus-Free Fertilizer|150|3.4|
 |Straw Mulch|4,000|90| |Straw Mulch|4,000|90|
 +|Wood Chip Mulch|12,000|270|
  
 :!://Detailed construction schedule must include all elements of erosion control and stormwater management plan, consistent with dates from the soil loss calculation.//:!: :!://Detailed construction schedule must include all elements of erosion control and stormwater management plan, consistent with dates from the soil loss calculation.//:!:
  
 **Construction Schedule** **Construction Schedule**
-  - Install erosion control devices and construct sediment traps. Contact Dane County Land & Water Resources within 10 days. (xx/xx/xx)+  - Install erosion control devices and construct sediment traps. (xx/xx/xx) 
 +  - Contact Dane County Land & Water Resources within 10 days after erosion control practices are installed.
   - Strip and stockpile topsoil. Install perimeter protection around stockpile. (xx/xx/xx)   - Strip and stockpile topsoil. Install perimeter protection around stockpile. (xx/xx/xx)
   - Rough grade lot and excavate for building foundation. (xx/xx/xx)   - Rough grade lot and excavate for building foundation. (xx/xx/xx)