| - Temporarily stabilize disturbed areas that will remain inactive for 14 days. | - Temporarily stabilize disturbed areas that will remain inactive for 14 days. | ||
| - Permanently stabilize any portion of the site within 7 days of reaching final grade. | - Permanently stabilize any portion of the site within 7 days of reaching final grade. | ||
| + | - Install and maintain a concrete washout. Chute washwater may not be dumped on the ground. | ||
| - De-watering shall conform to DNR Technical Standard 1061 and may not increase erosion. | - De-watering shall conform to DNR Technical Standard 1061 and may not increase erosion. | ||
| - Remove accumulated sediment from ditch checks and stone weepers when it reaches 1/2 of the device height. | - Remove accumulated sediment from ditch checks and stone weepers when it reaches 1/2 of the device height. | ||
| Line 41: | Line 42: | ||
| **Construction Schedule** | **Construction Schedule** | ||
| - | - Install erosion control devices and construct sediment traps. Contact Dane County Land & Water Resources within 10 days. (xx/xx/xx) | + | - Install erosion control devices and construct sediment traps. |
| + | - Contact Dane County Land & Water Resources within 10 days after erosion control practices are installed. | ||
| - Strip and stockpile topsoil. Install perimeter protection around stockpile. (xx/xx/xx) | - Strip and stockpile topsoil. Install perimeter protection around stockpile. (xx/xx/xx) | ||
| - Rough grade lot and excavate for building foundation. (xx/xx/xx) | - Rough grade lot and excavate for building foundation. (xx/xx/xx) | ||