Line 25: | Line 25: | ||
{{ : | {{ : | ||
- | The Dane County Erosion Control and Stormwater Management Ordinance sets management standards to attenuate the adverse impacts of stormwater. | + | The Dane County Erosion Control and Stormwater Management Ordinance sets management standards to attenuate the adverse impacts of stormwater. |
{{ : | {{ : | ||
Line 70: | Line 70: | ||
|[[Dry Pond]]|80% TSS; 40% TSS; Rate Control|Widely applicable, Larger drainage areas needed |Low to Moderate|Provides less water quality improvement than wet pond|Sufficient/ | |[[Dry Pond]]|80% TSS; 40% TSS; Rate Control|Widely applicable, Larger drainage areas needed |Low to Moderate|Provides less water quality improvement than wet pond|Sufficient/ | ||
|[[Gabion]]|80% TSS; 40% TSS; Stable Outlet|Widely applicable|Low to Moderate|Does not remove smaller suspended solids|Carefully size stone| | |[[Gabion]]|80% TSS; 40% TSS; Stable Outlet|Widely applicable|Low to Moderate|Does not remove smaller suspended solids|Carefully size stone| | ||
- | |[[Grassed | + | |[[Vegetated |
|[[Infiltration Basin]]|Infiltration; | |[[Infiltration Basin]]|Infiltration; | ||
|[[Infiltration Trench]]|Infiltration; | |[[Infiltration Trench]]|Infiltration; | ||
Line 89: | Line 89: | ||
====Runoff Rate Control==== | ====Runoff Rate Control==== | ||
- | The ordinance requires that all stormwater facilities be designed, installed and maintained | + | The ordinance requires that all stormwater facilities be designed to maintain |
- | *Maintain | + | |
- | | + | **NRCS MSE4 Storm Distribution** |
- | | + | |
- | | + | ^Frequency |
- | | + | |1|2.49| |
+ | |2|2.84| | ||
+ | |10|4.09| | ||
+ | |100|6.66| | ||
+ | |200|7.53| | ||
+ | |500|8.94| | ||
The ordinance requirements for water quantity apply to individual sites and not the entire watershed. | The ordinance requirements for water quantity apply to individual sites and not the entire watershed. | ||
Line 132: | Line 137: | ||
The ordinance requires that discharges from new construction sites have a stable outlet capable of carrying designed flow at a non-erosive velocity. | The ordinance requires that discharges from new construction sites have a stable outlet capable of carrying designed flow at a non-erosive velocity. | ||
- | Stable outlets are an integral part of well-designed erosion control and stormwater management practices. | + | Stable outlets are an integral part of well-designed erosion control and stormwater management practices. |
Stable outlets must have the capacity to handle the designed outflow from the stormwater or erosion control structures they serve. | Stable outlets must have the capacity to handle the designed outflow from the stormwater or erosion control structures they serve. | ||
Line 138: | Line 143: | ||
===Conveyance=== | ===Conveyance=== | ||
- | To prevent [[grassed waterway]] from eroding, an analysis of the channel velocity must be performed to determine the required control practice(s). | + | To prevent [[vegetated swale|vegetated swales]] from eroding, an analysis of the channel velocity must be performed to determine the required control practice(s). |
Culverts under private drives must be designed to convey the 10-year design storm, while those under public roadways must be designed to convey the 25-year design storm. | Culverts under private drives must be designed to convey the 10-year design storm, while those under public roadways must be designed to convey the 25-year design storm. |