As‐built certification, prepared by a Professional Engineer, is required within 10 days following installation of all stormwater management practices to ensure that the site was developed in accordance with the approved plan.
Certification must include the following:
If the site was constructed differently than the approved plan, additional documentation must be provided showing that the site is still meeting applicable ordinance requirements and standards. Significant changes to an approved stormwater management plan require a permit revision request prior to as-built certification. The addition, removal, alteration or relocation of best management practices is typically considered a significant change.
A record drawing is the final compiled drawing prepared by an engineer after completing a project. This drawing shows the final as-built or as-constructed condition to ensure that the project was built to the submitted and approved plans. The record drawing must include the following:
Checklists are intended to provide guidance to the design engineer and assist in expediting the review process. Additional documentation may be warranted depending upon how checklist items are addressed.
Photos of all complete practices listed in the maintenance agreement must be included. It's recommended that progress pictures also be provided.
The certifying engineer will submit the as-built package electronically, which will then be reviewed by staff for completeness. A site inspection will also be performed to verify site conditions. Additional information and/or corrections may be requested to ensure the site is meeting all stormwater requirements. Once approved, the site will be considered in compliance with its stormwater management permit and regular maintenance, as outlined in the recorded maintenance agreement, will be required.