Infiltration Practices

Infiltrating stormwater runoff is a great way to reduce the amount of water and pollutants reaching our lakes and streams. There are three primary practices that may be used for infiltration, but which one should be used on your site? The table below summarizes design guidelines to help choose the appropriate practice. Once a practice is selected, more specific guidance and requirements can be found on their individual pages.

Rain GardenBioretention DeviceInfiltration Basin
Watershed Size≤3,000 Ft2 Impervious, ≤5,000 Ft2 Total<2 Acres5-50 Acres
PretreatmentNot RequiredNot Required60% Residential, 80% Commercial
Drawdown Time<24 Hours≤24 Hours Surface, 72 Hours Total≤24 Hours
Surface LayerMulchMulch or Class II MattingNot Required
Engineered Soil LayerNot Required24 InchesNot Required
Storage LayerNot RequiredRequired if native infiltration rate <3.6 in/hr, ≤48 InchesNot Required
UnderdrainNot RequiredRequired if Native Infiltration Rate <3.6 in/hrNot Required
VegetationNative plant plugs or seed recommended. Turf grass allowed.Native plugs placed 12 in apartNative seed recommended. Turf grass allowed
Applicable StandardsInfiltration\Thermal\Green InfrastructureInfiltration\Sediment\Oil & Grease\Thermal\Green InfrastructureInfiltration\Thermal\Green Infrastructure